Ongoing Projects

Rehabilitation of Dock 22&23 at İzmir Port
  • Construction of 161,40 m. x 26,50 m.Quay
  • Dredging, 75.000 m³
  • Concrete Pavement, 16.000 m²
  • Filling, 125.000 m³
  • Jet Grout, 42.000 mt.
  • Soil improvement with Wick Drain, 190.000 mt.
  • 145 pieces D: 1219,2 mm T:12 mm  Steel Piles,
  • Construction of Bored Pile Quay, 61 pieces Ø 100 cm.
T.C.D.D.
18.08.2021 - 28.05.2022